Schedule of defects
A schedule of defects (or defects schedule) is issued by the contract administrator at the end of defects liability period. It identifies defects (aspects of the works that are not in accordance with the contract) that have become apparent during the defects liability period.
The contract administrator and the contractor then agree a reasonable period within which the contractor will rectify the defects identified on the schedule. Once the contract administrator is satisfied that the defects have been rectified, they issue a certificate of making good defects which has the effect of allowing the final certificate to be issued, releasing any remaining retention.
It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is a period during which the contractor may be recalled to rectify defects which appear. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued. See the article on practical completion for more information.
NB: Under NEC contracts, at, or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no patent defects, or lists any uncorrected defects. This is analogous to the schedule of defects. See Defects certificate for more information.
[edit] Related articles on Designing Buildings
- Certificate of making good defects.
- Contract administrator.
- De minimis.
- Defects.
- Defects certificate.
- Defects liability period.
- Handover to client.
- Latent defects.
- Liquidated damages.
- Migration strategy.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Protecting and storing rebar.
- Punch list.
- Remedial work.
- Retention.
- Schedule.
- Schedule of condition.
- Site inspection.
- Soft landings.
- Substantial completion.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.
The hidden risk in modern construction supply chains.
Construction Management, 10 June
24 months to 14: CITB launches accelerated apprenticeships.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
















